Factors of conflict between owner and contractor leading to project delay in Ho Chi Minh City

  • Minh Nguyen Tri
  • Long Le Hoai
Keywords: Conflicts, Ranking analysis, Delays, HCMC

Abstract

The construction industry plays a significant role in the national economy. It determines the size and technical level of the country's society and the industrialization and modernization in the current period. Vietnam is currently on the path of industrialization and modernization. Large corporations accumulate large capital and solutions to maintain their performances, or they rely on many sources of support to aim for development. In addition to large corporations, small and medium-sized companies and contractors have continued to struggle to survive. Accompanying this problem and including the contradictions caused difficulties are the causes leading to delays and failures in the construction industry in particular. Therefore, to help small and medium-sized enterprises, companies should have a better management direction and grasp The Factors of Conflict Between Investors and Contractors that Cause Delays in Construction.

điểm /   đánh giá
Published
2022-04-28
Section
THÔNG TIN VÀ GIẢI PHÁP KHOA HỌC, CÔNG NGHỆ